New incineration plant Environmental Engineering
Case:Muzha garbage incineration plant fly ash washing mold works
Owner:Taipei City Government Environmental Protection Agency
Major work:Improve the working of fly ash washing equipment design procurement installation and commissioning etc
Working areas:Muzha Refuse
Period:2009.11~ 2010.6
Case:Construction of Beitou Refuse Incineration Plant fly ash washing plant
Owner:Taipei City Government Environmental Protection Agency
Major work:Fly ash washing plant and wastewater treatment design procurement installation and commissioning work
Working areas:Beitou Refuse
Period:2010.7~2011.6
Case:Neihu plant fly ash receiving equipment and Beitou plant fly ash receiving device works
Owner:Taipei City Government Environmental Protection Agency
Major work:Neihu plant fly ash receiving equipment design procurement installation and commissioning of equipment and Beitou plant fly receiver equipment
Working areas:Neihu Refuse / Beitou Refuse
Period:2011.7~2012.6
Case:Union power plant waste oil water treatment equipment
Owner:Taiwan Power Company
Major work:Union power plant waste oil water treatment equipment design procurement construction commissioning work
Working areas:Shie-Ho Power
Period:2008.8~2009.2
Case:Taiwan high speed rail Nan-gang line-Core mechanical and electrical engineering
Owner:Toshiba Corporation
Major work:Preparations along the core electrical and mechanical engineering electrical design valuation interface integration
Working areas:Taipei city
Period:2010.8~NOW
Case:Public ducting construction plant
Owner:Formosa Petrochemical Corporation
Major work:RSG、SUS Prefabricated assembly, installation and protection
Working areas:Yun-lin county
Period:2012.6~NOW